A new law extends WV's long pattern of state preemption from extractive industry to data centers, stripping counties and towns of authority over certified projects and leaving communities with no information and only a fraction of the tax revenue.

This page introduces the legislative landscape at play in West Virginia data center and microgrid development and what is means for local communities.

The laws

Three laws shape how a data center gets sited in West Virginia. HB 2014 is the one that matters most. It lets the state certify a project in 14 days, removes county authority over it, and denies the public the right to disclosure of project information.

HB 2014: the Power Generation and Consumption Act

Passed April 12, 2025. In effect since July 11, 2025.

Project Certification Two tracks, both decided by the Secretary of Commerce
The two certification tracks
High impact data centerMicrogrid district
Who qualifies90 MW or more of critical IT load, in service on or after July 1, 2025An area up to 2,250 acres
DecisionThe Secretary “shall” certifyThe Secretary “may” certify
What is judgedOnly whether the project meets the definitionEconomic impact, and need to attract at least two businesses
Deadline14 days after notificationNone stated
LimitNoneTwo districts, unless over 70% of power goes to data centers
Code section§5B-2-21a, §11-6N-2§5B-2-21

Power companies inside a microgrid district are exempt from Public Service Commission oversight of rates, certificates, and complaints. The statute says the Secretary’s decision on a district “is final.”

Source: HB 2014, enrolled

Preemption of Local Control §5B-2-21b preempts local authority over certified projects

The Legislature states its intent “to occupy the whole field.” Counties and towns may not enact, adopt, implement, or enforce any rule that limits a certified project “in any way.” Certified projects are exempt from:

  • Zoning, noise, lighting, viewshed, development, and land use ordinances
  • County building permits, inspections, and code enforcement
  • County licensing
  • County or municipal legal jurisdiction, except as the article provides

Source: W. Va. Code §5B-2-21b

Transparency Public records exemptions

"Any information provided by a data center pursuant to this section that is identified by the data center as confidential business information shall be exempt from the Freedom of Information Act."

The state keeps a list of certified data centers for the Governor and Legislature, with identifying details removed. The law does not require the list to be public.

Still public: environmental permit records, utility contracts filed with the Public Service Commission, and county deed and tax records — although parts of these are typically redacted.

Source: W. Va. Code §5B-2-21a(e), §5B-2-21(h)

Taxes Data center incentives and local benefit

Most of the economic benefit from data centers is from taxes. One WV law provides data centers with a 95% tax break and another siphons 70% of the remaining tax revenue to the state.

High-Technology Business Property Valuation Act:

  • Taxes data center and microgrid tangible personal property at salvage value, or 5% of the actual value
  • Exempts data center and microgrid projects from sales tax for "all purchases of prewritten computer software, computers, computer hardware, servers, building materials and tangible personal property for direct use in a qualified high-technology business."
HB 2014 redistributes the remaining tax revenue 5 ways:
  • 50% to a Personal Income Tax Reduction Fund
  • 30% to local communities where projects are located
  • 10% to counties per capita
  • 5% to an Electric Grid Stabilization Fund
  • 5% to a State Economic Enhancement Grant Fund

Note: Of the total property tax revenue collected from data center projects, local communities will receive 30% of 5%, or 1.5% of the property value.

Roll call: final passage of HB 2014 See which officials voted for the bill

The full roll call for final passage, member by member. Choose a chamber to see who voted for it. Please note that this was voted on in 2025, meaning if you district is not there - the official resigned or moved on.

Don't know your district or official? Click here.

Loading the Senate roll call…

Loading the House roll call…

HB 4983 and the certification rule

Passed 2026. Authorizes the rule, 145 CSR 20, that sets what an application must contain.

The inordinate burden provision Disclosure is required. Acting on it is not.

Applicants must identify any physical or geological condition that could place an inordinate burden on a parcel within one mile, and say what, if anything, they would do to offset it. The Legislature added loss of access to water to that definition. The Secretary must consider proximity to schools, churches, homes, businesses, and historic sites.

The rule does not require the Secretary to deny certification over a burden, and offsetting one is optional. Petitions are confidential, so residents cannot read what was disclosed.

Source: 145 CSR 20, §2.4; HB 4983

Water: no permit, no advance disclosure What DEP told legislators

DEP officials testified that the state has no permitting program for large water withdrawals and cannot control where a developer draws from. Amendments to require advance reporting were rejected in committee and on the House floor.

Large users must register their use after the fact (§22-26-6). Nothing requires disclosure before withdrawals begin, though state law declares the waters a public resource held for citizens (§22-26-3(a)).

Source: W. Va. Code §22-26-3, §22-26-6; Charleston Gazette-Mail, March 2026

Public comment on the bill 39 comments, all opposed

All 39 public comments we reviewed on HB 4983 opposed it. The House passed it 78 to 16.

Source: HB 4983 bill history; [public comment record]

HB 2002: One-Stop-Shop Permitting

Passed April 9, 2025. In effect from passage.

What it changes Faster permits for applicants; nothing new for the public
  • An online Permitting Dashboard for state permits, due by January 1, 2027.
  • Applicants can pay extra to fast-track a permit.
  • Agencies that miss processing deadlines must refund fees, starting 2027.
  • The dashboard becomes the only way to apply after July 1, 2027.

The law lists transparency as a purpose, but the features it describes are for applicants. It does not say whether the public can see pending applications, and it does not change any comment period.

Source: HB 2002, enrolled, §5A-13-1 to §5A-13-6

Zoning in West Virginia

About 78% of all jurisdictions and 81% of state's total acres are unzoned. In the Eastern Panhandle, Jefferson County is almost entirely zoned. Berkeley and Morgan are almost entirely not.

Land use management by county
County Unzoned Zoned Protected
West Virginia80.6%9.0%10.4%
Berkeley89.5%1.8%8.6%
Jefferson4.8%90.5%4.7%
Morgan90.3%0.0%9.7%

Percent of county land area; rows may not total 100 because of rounding. Protected means protected public land. Source: National Zoning Atlas, West Virginia.


How a county adopts zoning Optional, and subject to a voter petition

Zoning is opt-in. A county must first adopt a comprehensive plan, form a planning commission, and hold hearings. The county commission can then enact a zoning ordinance or put it to a vote.

If it enacts the ordinance without a vote, residents have 90 days to gather signatures from 10 percent of eligible voters. If they do, the ordinance only takes effect if a majority approves it.

Since July 2025, none of this applies to a certified project, whether the zoning already existed or is adopted later.

Source: W. Va. Code §8A-7-7; §8A-7-8a

Before and after HB 2014 The Kearneysville Project is not HB2014 certified. The Bedington Project is.
Local review of the Eastern Panhandle projects
KearneysvilleBedington
Approved byBerkeley County Planning CommissionWV Secretary of Commerce
WhenMarch 2025, before HB 2014February 2026, after HB 2014
County land use mapGrowth area with industrial designationConservation and rural uses, no industrial designation
County reviewYesNone

Source: [Planning Commission minutes, March 2025]; [Berkeley County Comprehensive Plan, Future Land Use Map]

Local Ordinances

Jefferson County is almost entirely zoned, and despite a lack of zoning Berkeley County, there are still local rules in place to guide and regulate land use management.

Berkeley County Comprehensive Plan

Berkeley County is adopting Berkeley: Prospering Together, the plan that will guide land use for the next 5 years. The theme is largely shaped by resident input: 78% of survey respondents named rapid growth as their top concern, and the plan's vision commits the County to "grow and prosper while preserving its natural resources, tight-knit community, and exceptional quality of life." That is a strong foundation. On data centers, however, the plan offers no protections, and the public hearing is the time to change that.

What the plan gets right

  • Clear maps of where growth belongs. The plan sorts the County into Conserve, Sustain, and Grow areas. Public utilities are not to be extended into Conserve or Sustain areas. Conserve areas are meant to be "protected from development," and in Sustain areas the plan states plainly that "new, large subdivisions and industrial uses are not appropriate."
  • The Bedington site is not marked for development. The County's own GIS suitability analysis (Map 8.1) labels the site an unsuitable development area, and the Future Land Use Map (Map 8.2) places it in Conserve/Sustain. The County's own data supports keeping this land as it is.
  • Water protection. The plan calls for the Berkeley County Public Service Water District to review site plans so that new development is not permitted without measures to safeguard source water and address water system capacity (Strategy 3.4.2).
Map 8.1, Berkeley County Development Suitability. Red marks areas unsuitable for development, including floodplains, steep slopes, 
			conservation easements, and Sleepy Creek Wildlife Management Area along the western border. Olive shading marks the most suitable areas, 
			concentrated along the Interstate 81 corridor and around Martinsburg.
Map 8.1: Development Suitability. The County's GIS analysis. Red areas are unsuitable for development; olive areas are most suitable, mostly along I-81.
Map 8.2, Berkeley County Future Land Use Map. Green Conserve areas cover the western mountains and land along the Potomac River 
			and the eastern edge of the county. Blue Sustain areas surround a central yellow Grow corridor that follows Interstate 81 and Route 11 
			through Martinsburg.
Map 8.2: Future Land Use. Green is Conserve, blue is Sustain, and yellow is Grow. Growth is directed to the I-81 corridor.

Maps: Berkeley County Comprehensive Plan Final Draft (Sept. 8, 2026), pp. 87 and 94. Select a map to view it full size.

What the plan lacks

Data centers appear once in the plan's strategies, in the economic development chapter:

"Prepare for data center development by ensuring that planned industrial areas have adequate utilities and infrastructure and work with the state legislature to promote smart siting policies and adherence to community priorities and future land use planning."

There are no standards for water use, power demand, noise, setbacks, or public notice. Residents raised these concerns during the planning process and in the final public hearing.

The maps alone will not protect Bedington

  • The plan is guidance, not law. It does not carry regulatory force on its own.
  • Berkeley County has no countywide zoning. Zoning covers only two small districts, so the Future Land Use Map has little to enforce it.
  • The plan admits state law can override it. In its own words, "certain West Virginia state and federal laws can override or significantly limit the County's ability to conserve land by requiring siting of certain large commercial and industrial uses." Learn how state law affects local control.

Local Action

Several community members showed up to the public hearing to comment on th plan. Speakers raised concerns over a lack of data center guardrails and the lack of a mechanism that enforces the plan's vision. The commission was asked to directly address data center development with the addition of guardrails modeled after the document that passed the Jefferson County Commission unanimosly on October 1, 2026.

View the full Berkeley County Comprehensive Plan .

Jefferson County Good Neighbor Data Center Guardrails

Jefferson County Good Neighbor Data Center Guardrails.

What happened, and when

The laws, the rule, and the two Eastern Panhandle projects in order.

Show

2025

  1. March

    Berkeley County approves the Kearneysville concept plan

    Berkeley County Planning Commission

  2. April 9

    HB 2002 passes and takes effect

    Legislature

    HB 2002, enrolled

  3. April 12

    HB 2014 passes

    Legislature

    HB 2014, enrolled

  4. July 11

    HB 2014 takes effect

    County authority over certified projects ends

  5. November 10

    Commerce files the certification rule as an emergency rule

    Takes effect within weeks, without the inordinate burden language

  6. November 17

    Bedington Owner LLC registers to do business in West Virginia

  7. December 10

    Comment period on the rule closes, with about 935 comments

    Department of Commerce

2026

  1. January 29

    Rule refiled with the inordinate burden provision

    After objections from the Legislative Rule-Making Review Committee

    HB 4983

  2. February 17

    House passes HB 4983, 78 to 16

    Water reporting amendments rejected

    Bill history

  3. Nov 2025 – Feb 2026

    No public notice, hearing, or comment found on Bedington

    HB 2014 does not require pubic notice

  4. February 26

    Bedington becomes the state’s first certified data center

    548 acres, certified under the emergency rule

  5. March 27

    Governor approves HB 4983; the rule becomes final

    Governor

    Bill history

  6. September 21

    Final draft County Comprehensive Plan approved during a public hearing of the Planning Commission.

    The Comprehensive Plan designates the site where the Bedington Project is located as Sustain/Conserve and unsuitable for development.

  7. October 22

    Berkeley County Commission Public Hearing on Comprehensive Plan Final Draft.

    Local residents expressed concerns over a lack of data center guardrails and enforceability of the county land use management plan.

    See the Bedington page for more information

Notice and comment

Legal notice and effective notice are different things. A requirement can be satisfied in full while almost no affected resident learns of it.

What notice the law requires
DecisionPublic noticeComment period
Data center or microgrid certificationNoneNone
State air permitOne newspaper legal ad30 days; a public meeting can be requested
Army Corps individual permitPosted online by the district15 to 30 days
Army Corps nationwide permitOften none for the specific projectOften none
Utility special contractPublic Service Commission docketThrough the case